Completion and compliance works at Palazzo Gallenga to fire safety regulations and air conditioning systems and extraordinary maintenance and restoration of the terrace, the roof and the bathroom units
- Decree of the Director General No. 145/2026 - Protocol No. 5869 of 12/03/2026 (succession)
- Decree of the Director General No. 322/2025 - Protocol No. 0015997 of 01/08/2025 (payment of SUA charges)
- Decree of the Director General No. 298/2025 - Protocol No. 0014947 of 17/07/2025 (award)
- Decree of the Director General No. 259/2025 - Protocol No. 003496 of 01/07/2025 (payment of ANAC charges)
- Rectoral Decree No. 287/2025 - Protocol No. 0012329 of 16/6/2025
- Decree of the Director General No. 48/2025 - Protocol No. 004638 of 26/02/2025
- Rectoral Decree No. 547/2024 - Protocol No. 27197 of 20/12/2024 (approval of fire safety documents)
- Resolution 237/2024 - Protocol No. 26945/2024 of 18/12/2024 (conditional approval of the executive project, adjustment of the funding and authorization to start the tender)